Hamburger Hungaria - erection PM 7
Erection of a fluting- and testliner paper machine
![]()
Customer:
W. Hamburger Papirgyarto KFT, Hungary
Project:
Name: Erection of a fluting- and testliner paper machine
Start-up: June 2009
Annual production: 350.000 tpy (paper width 7.800 mm)

Planning contract:
TBP has been engaged as turnkey engineering planner, including civil engineering.
The plant engineering comprises waste paper storage until roll storage
- Preliminary project and approval engineering for authority
- Purchasing for plants and E&I
- Basic- and detail engineering
- Erection and start-up planning incl. supervision
- CE-Documentation
Scope of planning:
Preliminary project and approval engineering for authority: approx. 6.000 hours
Purchasing and engineering: approx. 64.000 hours
Supervision of erection: aprrox. 14.000 hours
Implementation period:
Engineering: 11/2006 to 09/2008
Supervision of erection and start-up: 09/2008 – 07/2009
Start-up: June 2009